Tuesday, May 29, 2012

29th May 2012





            I’m loosing track of time and I don’t think it’s got anything o do with age, over the past two or three weeks a crane with forks on the front came and unloaded a truck of plaster board, lifting it up to the scaffolding at the front balcony where the plasterers slid it off into the lounge sheet by sheet. They have to use a crane for this activity, as the long sheets apart from being very heavy are just too long to get up the stairs to the upper level, a similar amount was manoeuvred into the garage for downstairs.

External rendering has also taken place over the last couple of weeks although they still have a little area to finish at the front once the triangular window is installed. In a nutshell, rendering over the special building foam cladding consists of an application coat of specially mixed cement render engulfing a fibre glass mesh mat that looks a bit like bird cage wire, following this they apply an acrylic based top coat containing a grit compound to give the desired render finish depending upon which grade of compound has been selected. Later it will have a couple of coats of paint the colour we previously selected. Apparently the whole process, foam and render results in a very strong, waterproof cladding that is straight and true and well insulated, the foam being 75mm thick at least, and reasonably dense much like the foam boxes they transport veges and seafood in only thicker. In addition to this the wall cavities between studs and noggins on the inside of exterior walls are all packed with fibre wool (pink bats) for additional insulation and sound reduction, while they were at it we had the walls and ceiling insulated between in our bedroom.

Plaster installation on the inside of the house has been completed other than the cornice piece (that is the curved bit where the walls meet the ceiling). They seem to have an expert for each application, two people put up the sheets of plaster-board walls and ceilings. Then another couple did the taping and filling of joints and nail locations, yet to come are others to install the cornice and finish those. After all that is done another team come and sand all the filled areas smooth and flat, then I guess it’s ready for the painters although I imagine they can’t start until skirting are installed and that can’t be done until the timber floor is laid. Gee I‘ve got a lot of supervising to do!!!

Plumber came yesterday and installed downpipes etc and today the foam guys are back applying sealants around all of the windows, joints and cavities to ensure everything is watertight, (so it won’t sink). Chippies are back today and will probably be here to completion, they’re currently hanging doors and finishing soffits and will complete any jobs that require scaffolding while it is still in place.

I’m busy replacing hose clamps on the Toyotas power steering in a process of elimination to stop air ingress into the system, a power steering specialist told me the noisy growling in my steering wasn’t Nancy having a go at me but was air getting into the system. If the hose clamps don’t do the trick the pump has to come off to replace ‘O’ rings, $$$$. Just changing hose clamps is a hell of a job, who would be a mechanic, you have to half strip the car from underneath to get a look at anything then you can’t get your hands into where you want to and everything is always behind something else, bugger of a job. Without taking hoses off and losing all of the oil it is a nightmare trying to get the old sprung clips off, under the car crap falling into your eyes and you can’t reach it anyway. Wish I was rich.
I have to go  and finish the job I started SWHTBO has informed me the car is required.


Stay cool

Nigel




Lifting in the plasterboard

Ceilings first

Applying the render



Mixing render

Nothing like modern equipment

Plasterboard well under way

Internal insulation and soundproofing

Front view most of the rendering completed 

Back view completed rendering

No comments:

Post a Comment